COVID-19: Managing project delays and claims

0
1891

By James LeBer and Marcia Oliver

Advocates LLP argues that Notice of Delay given now and tied to Ontario’s March 17 declaration of a State of Emergency and related MOH social distancing directives may allow you access to a compensable delay, rather than merely an excusable delay.  This article was originally distributed by the firm to its large base of general contractor clients as a “Client Alert” on March 22. It is republished here with the permission of the authors.

            Ontario Construction News is publishing the article in two parts. The second part, which will be published in an upcoming issue, focuses on specific issues relating to outdoor work with a focus on Ministry of Transportation projects

Overview

These are indeed challenging times. What lies ahead is unknown for all of us. Things will be particularly challenging for the construction industry given the complexity of factors which must come together to ensure the successful completion of a project. The construction industry makes significant contributions to our economy; and so it is imperative that all participants in the industry work collaboratively to keep projects going, at least where it is safe to do so; and where projects are suspended, to manage any claims arising in an efficient and effective manner.

In response to the many questions we have received from our clients over the last week or so, we have developed a “roadmap” to help guide you through some potential legal impacts of COVID 19 and provide you with some recommendations to assist you as you navigate these uncertain times.

These comments are intended to help you in your consideration of the available steps to be taken in light of COVID 19 concerns. They are premised upon two common contract formats used by many of our clients in the ICI Sector. Our comments are of a general nature only and are not, and should not, be relied upon as legal advice.

Our whole team at Advocates remains “at work” though we are doing so remotely these days, to comply with both the declared state of Emergency and related Public Health orders. We are available to you to review your specific contract language and discuss your specific circumstances as together we seek to develop an optimal strategy to keep your forces safe on site, and attempt to position your company for the challenging days ahead, to the extent that relief may be available under your own unique contract provisions.

Where do you start?

We are not experts in infectious diseases. However, we do know that to avoid or curtail the spread of COVID 19 limiting or preventing close contact in confined spaces is essential. And as we also know for some spaces, like restaurants and schools, the governments have mandated closures. That has not been the case in the construction industry – yet.

How and/or whether you proceed with your particular project will be influenced by a number of factors; including the environment in which the construction is taking place. For example: are you engaged in construction in an enclosed environment (ie: building construction); or, are you engaged in construction in a non-enclosed environment (ie. road building?). The risk profile will be different and unique to each project.

However, in consideration of how you move forward, we know you always recognize that the key factor in your analysis is the health and safety of your own workers, and the health and safety of all the persons on the jobsite, and the public at large. Your consideration of the health and safety of workers is both your moral obligation and also your legal right and obligation.

General principles of Occupational Health and Safety

Occupational Health and Safety remains a foundational principle which will govern all conduct on the job site. As you well know you are obliged to take all reasonable steps to ensure your site is, and remains, safe for workers. Employees have the right to refuse to perform work where they hold a bona fide belief that they may not be safe.

Under the Occupational Health and Safety Act s.37, an employer is obliged to disclose the presence of hazardous materials in the workplace.

If the project site is a functioning hospital facility and the Constructor cannot be satisfied that its work force is not at risk of exposure to individuals with COVID 19 this may form a basis for refusal to work. Such a contractor may have General Conditions such as those found under the CCDC2 contract which deal specifically with hazardous materials. Those provisions require careful consideration based on the specific facts of your job site, and we urge anyone contemplating relying upon these clauses to immediately obtain legal advice.

Specifically, under Part V of the Occupational Health and Safety Act – s. 43 (3): a worker may refuse to work, or to do particular work where they have reason to believe that the physical condition of the workplace is likely to endanger them. There are exceptions to this right that apply to workers whose work is inherently risky, or to those whose refusal would directly endanger the life, health or safety of others, such as police, firefighters, or hospital workers. In these challenging times, we are grateful for those who have chosen to assume these risks for the benefit of the greater good.

We have heard reports of workers in certain circumstances and on certain projects refusing to work over concerns about COVID 19 health and safety concerns at the job site. We are aware of concerns for emerging and pending labour shortages. Product supply shortages will inevitably follow, since the manufacturers and those downstream in the supply chain will face the same impacts on their own workforce, assuming they have managed to remain open and operational in this difficult time.

The contract

Every contract is unique and the facts are often as important as the terms of the contract. Below we have highlighted common provisions contained in the CCDC-2 Contract and in OPSS Contracts that you should be aware of; and we have noted how such provisions may be applicable to the current issues at hand. Of course, standard contracts may have been amended by supplementary conditions, as such it is important to read your contract thoroughly before you take any steps.

Giving Notice of Delay and requesting extensions of time

The government of the Province of Ontario declared a State of Emergency on Tuesday March 17, 2020 closing many different businesses. It banned public events of more than 50 people in the declaration, which reinforced the Ministry of Health (MOH) directives to invoke social distancing measures, requiring people to remain a minimum of 2 metres from one another, and to self-isolate for 14 days in the event of illness or potential exposure to an ill person.

Maintaining a sustained work force, and also achieving historical productivity levels, seems to no longer be possible in the medium term. The full extent of the ongoing impacts cannot be determined, but there are and will continue to be real impacts to projects underway and those projects about to commence with the arrival of Spring conditions.

Regardless of your form of contract, we encourage you to be familiar with the various notice provisions – including when you must provide notice for a claim and what details must be included in the claim. While these are unprecedented times, you do not want to risk being denied a claim for compensation or relief from penalty, for failure to provide notice in accordance with the contract.

CCDC 2 contracts

These comments generally apply to clients constructing buildings where the likelihood of the work force having to operate in close quarters (<2 metres), or within a team in a more confined space seems generally to be greater than in the road and bridge building sectors.

The provincial government in the Province of Ontario declared its State of Emergency on Tuesday March 17, 2020 closing many different businesses and banning public events of more than 50 people and reinforcing the MOH’s declaration to invoke social distancing measures. This gives us a logical reference point to establish either the commencement of the delay under the CCDC2 GC 6.5.4 or alternatively to contemplate the threshold of “as soon as the need for an Extension of Time becomes evident” under GC 3.06.01 of the OPSS GC’s. It also anchors your notice to a series of events which we argue should be compensable.
Compensable delay – GC 6.5.2

A number of General Conditions may be triggered by issues arising with COVID 19 concerns. Under CCDC-2 we consider that the least risky of the avenues open to the contractor to give notice arises through GC 6.5 Delays.

(Raymond insert image Advocates fig 1)

Under GC 6.5.2 you can argue that a stop work order has been issued not by a Court but by another “public authority”, in the form of the declaration that people must not gather in numbers larger than 50 and should not be in closer proximity than 2 metres from one another. If either of these limitations to the way in which work on your site can be carried out, has a practical consequence of impacting productivity or entirely precluding certain tasks, then notice of delay may be given. If the same provisions are expected to cause material shortages, notice can be given. If the 14 day self-isolation obligation (triggered under various scenarios) is expected to cause labour shortages, notice can be given.

Under this provision the contractor may seek reimbursement from the owner for the costs incurred as a result of the delay, in addition to being granted further time and therefore relief from liquidated damages or other delay based penalty claims by an owner for late project completion.

You may expect from consultants or owners, an argument that the work has not been stopped by these “orders”, and that the GC 6.5.2 clause applies only to a total stoppage of work, not to “mere operational constraints” such as those imposed by Ontario’s declaration and MOH’s directives.

Our response to that is that these operational constraints do stop the work in both space and in time. They stop the work within specific job site locations – specifically for the second team member who would normally and most efficiently work within the 2 metred radius of every other worker then on site. They also stop the work of workers who feeling briefly ill but, unable to access any definitive test, must stay off work for two weeks, along with workers who, without being ill themselves are obliged to isolate due to potential of exposure to an untested individual who themselves felt ill or was subsequently diagnosed.

This is not a criticism of these measures, but a reflection that this new reality will produce labour shortages in a number of different ways which were not previously foreseeable. Tying your notice to the provincial declaration and MOH directives assists that argument.

GC 6.5.2 places this risk on the owner. Since COVID 19 was not a risk contemplated by the parties, we believe it can reasonably be argued that it could not have been transferred to bidders at time of contract formation. We see this GC as the preferred approach to dealing with these consequences and any resulting delays. Timely notice then, may be critical.

Force Majeure – GC 6.5.3.4

The alternative ground for delay would be GC 6.5.3.4 for delays suffered due to any cause beyond the contractor’s control, other than one resulting from a default or breach of the contract by the contractor. In that alternative scenario, the only relief is additional time with no compensation. It becomes an excusable but not compensable delay, which is not a contractor’s preferred course.

Critically – and in either case, Notice of the Delay must be given within 10 working days of commencement of the delay pursuant to GC 6.5.4.

(insert image advocates image 2)

The take-away here is that under CCDC-2 you must give Notice of Delay within 10 working days of commencement of the delay, and we recommend anchoring that Notice to Ontario’s March 17 Emergency Declaration and the related MOH directives on social distancing.

(insert Advocates image 3)

Concealed or Unknown Conditions – GC 6.4

There is a third avenue under CCDC 2 which invokes the provisions of the hazardous substances General Conditions. We consider it to be a high risk strategy for a contractor to rely on this provision because the party responsible for the presence of the hazardous substance on site is at risk of having to indemnify the other for the consequential cost impacts of managing that exposure. For that reason, we could only see it be given serious consideration by those contractors working at an active hospital site where patients with COVID 19 are passing close to the location of construction activities. Those circumstances arguably give rise to an identifiable and enhanced risk caused by the activities of the owner at the site.

The argument to be followed in such a case would arise with a Notice under GC 6.4 of a Concealed or Unknown Condition at the place of work. It would be a GC 6.1.4.2 unanticipated “physical condition… of a nature which differ materially from those generally recognized as inherent in construction activities…”

To initiate this process the contractor must give notice within five days of the observance of the conditions. Hence an immediate decision to give that notice must be made if this were to form the basis of the effort to seek time and compensation due to impacts. It should also be expected to lead to a process of engaging the Occupational Health and Safety Committee and Hospital Risk Management staff. It would be a protracted process, during which there would likely be at least a temporary suspension of work while the owner attempted to put in place further strategies to properly deal with the hazardous conditions.

(insert advocates image 4)

Under GC 6.4.4 it is contemplated that the unknown condition may relate to toxic substances, and if so, reference is then made to the operative provisions of GC 9.2 Toxic and Hazardous Substances

(insert advocates image 5)

The challenge and risk arising once the contractor directs the owner into GC 9.2 is that the pendulum can swing both ways. The concept established by GC 9.2 is to compel the party which is found to have introduced the toxic substance to the site, to bear all the consequences of steps necessary to address the impacts from the substance. The language is broad. It could be argued to apply to both direct clean-up costs, and consequential delay costs. Caution is therefore urged, before initiating such a process. The circumstances where it might succeed are likely restricted to those where the facility is a known treatment center for COVID 19 patients supporting the inference that an elevated toxic risk, was being brought to bear on the project due to the owner’s operations.

As you can see in the snip below, the GC 9.2 Toxic and Hazardous Substances sections also creates trailing obligations for indemnity, which should be a concern to any general contractor.

(advocates image 6)

A PDF copy of the complete original article may be downloaded here.

          Jim LeBer and Marcia Oliver are certified specialists in construction law and partners in the firm Advocates LLP, a construction and commercial litigation firm.

J.*****@Ad**********.com











and

M.******@Ad**********.com











, Advocates LLP, One London Place, 1620 – 255 Queens Ave., London ON N6A 5R8, phone: (519) 858-8220, fax (519) 858-0687.