Underground nuclear waste repository site to be selected in Ontario this year

0
1206
swami
Lori Swami, president and CEO of the Nuclear Waste Management Organization

The Canadian Press

A critical milestone is on the horizon for Canada’s 175-year-long plan to bury its nuclear waste underground, with two pairs of Ontario communities set to decide if they would be willing hosts.

Later this year, the Nuclear Waste Management Organization plans to select the site for Canada’s deep geological repository, where millions of bundles of used nuclear fuel will be placed in a network of rooms connected by cavernous tunnels, as deep below the Earth’s surface as the CN Tower is tall — if the process goes according to plan.

“As we end 2023, I am energized by the momentum Canada has built on nuclear waste management that we can now carry towards our next major milestone in 2024, selecting a site for our country’s deep geological repository,” Laurie Swami, president and CEO of NWMO said in a yearend community update. “In the past few months alone, we have made important progress on Canada’s plan for the safe, long-term management of used nuclear fuel, as well as new endeavours to manage radioactive waste — all driven by a continued commitment to collaboration and partnership.”

Once a site is selected, the NWMO estimates regulatory approvals will take about 10 years, and construction will take about 10 years. Used fuel will be loaded in over a period of about 50 to 60 years, then it will enter an “extended monitoring” phase that will last about 70 years.

“It will be up to future generations to decide: do we think we have all the data we need? And do we need to keep monitoring,” she said. “Or can we now close the facility up and seal the shaft.”

Ignace
Ignase

Potential sites are the Wabigoon Lake Ojibway Nation-Ignace area in northwestern Ontario and the Saugeen Ojibway Nation-South Bruce area in southern Ontario. The municipalities and First Nations are planning votes for next year, the culmination of a years-long information gathering process that some say has left deep divisions within their communities.

The process to move ahead with a deep geological repository is already more than 20 years along. The NWMO was established under legislation in 2002 and is funded by the corporations that generate nuclear power and waste, such as Ontario Power Generation and Hydro-Quebec.

While officials say they are confident at least one area will say yes, two rejections would be a major setback for the $26-billion project.

“Ultimately, if both areas say no, then we have to start over — and by we I mean Canada,” said Lise Morton, the vice-president of site selection.

“We as a country would then be really pushing the resolution of this issue to the next generation.”

Both the municipality and First Nation in the area of either proposed site must confirm willingness to host the repository before the NWMO will proceed.

In South Bruce, they are planning to hold a referendum late next year. The mayor sees great potential for direct and indirect job creation if the repository is located there.

“In this location we’ve kind of been left out of the major boom that Ontario has been seeing so far,” Mark Goetz said. “We’ve seen it to the west of us, to the Great Lakes, and we’ve seen it sprawling from Toronto to the east of us … but we haven’t really benefitted here a whole lot yet.”

South Bruce already has deep nuclear roots, with the Bruce Power plant close by. A refurbishment project there is set to wind down around when the repository project would start up, providing opportunities for tradespeople, Goetz said.

But there are a good number of people in the community who are not convinced — about 20 per cent are with Protect Our Waterways, the main opposition group, Goetz estimates — and it has caused “quite a friction.”

South Bruce
South Bruce

South Bruce is also in the shadow of Walkerton, Ont., where seven people died and thousands fell ill after drinking contaminated water in 2000. Fears about drinking water have lingered there long after the tragedy, said Bill Noll, vice chair of Protect Our Waterways.

“There is a big concern relative to water,” Noll said. “Once you pollute the water, there’s not much you can do about it.”

Water also weighs heavily on the minds of members of the Wabigoon Lake Ojibway Nation, who have seen members of another northwestern Ontario First Nation on the English-Wabigoon river system grapple with generations of mercury poisoning after a mill in Dryden dumped 9,000 kilograms of the substance in the 1960s.

“That’s the evidence right now of how an industry went astray or how government oversight wasn’t there,” said Wabigoon Lake Ojibway Nation Chief Clayton Wetelainen.

Within the planned repository, the radioactive materials would be under multiple layers of protection, and for contamination to happen, “everything has to fail,” said NWMO senior transportation engineer Ulf Stahmer. It’s a scenario he does not see happening.

The outermost layer of protection is the rock itself, with the repository about 500 metres down in a rock formation selected for its low permeability. Then come blocks of bentonite clay that encase further layers within. The clay forms a good seal and naturally attracts radioactive materials, so if any were to migrate through the other layers underneath, they would find it hard to make it past the clay, Stahmer said.

Bentonite clay also swells, creating a pressure that inhibits microbial corrosion, he said.

Packed within the bentonite clay will be containers made of carbon steel and coated with copper to prevent corrosion. Those containers have been subjected to crush tests with the weight of 500 to 700 metres of rock plus two kilometres of ice — designed to mimic a future ice age, Stahmer said.

“This container can then survive the repository for a long, long time … essentially forever,” he said.

Within the used nuclear fuel containers will be the fuel bundles, or rods, made of corrosion-resistant Zircaloy. Those bundles contain the actual fuel pellets, which look a bit like a thick watch battery. They are made from uranium dioxide powder and baked into ceramic, which doesn’t dissolve easily in water.

But all the tests and planning and modelling are not easing the fears of the project’s critics, either with the southern Ontario-based Protect Our Waterways or We the Nuclear Free North.

“The whole thing is a grand experiment,” said Brennain Lloyd, with the northern group.

“There’s not a deep geological repository … operating anywhere in the world. The NWMO likes to say, ‘Well, this is best international practice,’ but practice implies that it’s been done before. And there is no practice. Nobody has done this before.”

There are others in the works internationally, with Finland’s being one of the furthest along. The NWMO recently sent officials and community members from both possible Ontario sites on a trip to Finland to see that repository for themselves.

Jodie Defeo, an Ignace councillor, was on the trip and was awed at the scale of the project.

“It was physically daunting,” she said. “You could fit a car driving through the tunnels. It was very amazing to see.”

LEAVE A REPLY

Please enter your comment!
Please enter your name here

I accept the Privacy Policy